Cal Trans Pump Station

City of Fullerton: Storm Drain Pump Station

Project Details

Installation of (2) 6.100 GPM – 50HP submersible pumps and associated piping inside a 35’ deep wet well structure. Caliagua installed all piping including pipe supports, discharge vault, structural steel, and misc. site concrete work. Our scope also included all pump station electrical work. All work was completed to the satisfaction of Caltrans.